Which of the following common data points is required to calculate the demand factor and load factor?

This question was previously asked in
MPPGCL JE Electrical 28 April 2023 Shift 1 Official Paper
View all MPPGCL Junior Engineer Papers >
  1. Average load
  2. Connected load
  3. Contract load
  4. Maximum demand

Answer (Detailed Solution Below)

Option 4 : Maximum demand
Free
MPPGCL JE Electrical Full Test 1
3.9 K Users
100 Questions 100 Marks 120 Mins

Detailed Solution

Download Solution PDF

Explanation

The demand factor of a plant is calculated as:

\(Demand \space factor={Maximum \space demand\over Connected\space load}\)

The load factor of a plant is calculated as:

\(Load\space factor={Average \space demand\over Maximum \space demand}\)

In both formulas, the maximum demand is the common data points required to calculate the demand and load factors.

Latest MPPGCL Junior Engineer Updates

Last updated on May 29, 2025

-> MPPGCL Junior Engineer result PDF has been released at the offiical website.

-> The MPPGCL Junior Engineer Exam Date has been announced.

-> The MPPGCL Junior Engineer Notification was released for 284 vacancies.

-> Candidates can apply online from 23rd December 2024 to 24th January 2025.

-> The selection process includes a Computer Based Test and Document Verification.

-> Candidates can check the MPPGCL JE Previous Year Papers which helps to understand the difficulty level of the exam.

Get Free Access Now
Hot Links: teen patti master list teen patti 100 bonus teen patti all games teen patti sequence teen patti app