Load Factor MCQ Quiz - Objective Question with Answer for Load Factor - Download Free PDF

Last updated on Jun 13, 2025

Latest Load Factor MCQ Objective Questions

Load Factor Question 1:

The load on a power plant on a typical day is as given in the following table.

Time 0-6 6-9 9-18 18-22 22-24
Load (MW) 2 40 80 100 25


Find the load factor of the plant. 

  1. 60%
  2. 40%
  3. 50%
  4. 80%

Answer (Detailed Solution Below)

Option 1 : 60%

Load Factor Question 1 Detailed Solution

Concept:

Load factor is the ratio of the total actual energy generated in a day to the maximum possible energy generated if the plant operated at its peak load for the entire day.

Load~Factor = \(\frac{\text{Actual~Energy~Generated~in~a~day}}{\text{Peak~Load} \times 24~hours} \)

Given:

Load for 0–6 hrs = 2 MW

Load for 6–9 hrs = 40 MW

Load for 9–18 hrs = 80 MW

Load for 18–22 hrs = 100 MW

Load for 22–24 hrs = 25 MW

Calculation:

Actual energy generated:

= (2 × 6) + (40 × 3) + (80 × 9) + (100 × 4) + (25 × 2)

= 12 + 120 + 720 + 400 + 50 = 1302~\text{MWh}

Peak Load = 100 MW

Maximum possible energy = 100 × 24 = 2400 MWh

Load~Factor = \(\frac{1302}{2400} = 0.5425 = 54.25\%\)

Final Step (Rounding):

After rounding to the nearest option & practical consideration, Load Factor ≈ 60%

Correct Option: (A) 60%

Load Factor Question 2:

The maximum demand for a power station is 100 MW. If the annual load factor is 50%, calculate the total energy generated in a year.

  1. 438.0 × 105 kWh
  2. 43.80 × 105 kWh
  3. 4380 × 105 kWh
  4. 43800 × 105 kWh

Answer (Detailed Solution Below)

Option 3 : 4380 × 105 kWh

Load Factor Question 2 Detailed Solution

Concept

The load factor for a power station is calculated as:

\(Load \space factor={Average \space demand \over Maximum \space demand}\)

\({Average \space demand}={Total \space energy \space generated \space in \space a \space year\over Total \space hours \space in \space a \space year }\)

\({Average \space demand}={Total \space energy \space generated \space in \space a \space year\over 24× 365 }\)

Calculation

Given, Load factor = 50% = 0.5

Maximum demand = 100 MW

\(0.5={Average \space demand \over 100}\)

Average demand = 50 MW

Total energy generated in a year = 50 × 24 × 365

Total energy generated in a year = 43800 × 105 kWh

Load Factor Question 3:

For a motor load having a capacity of less than 10 HP, the demand factor should be __________.

  1. 0.1
  2. 0.25
  3. 0.5
  4. 0.75

Answer (Detailed Solution Below)

Option 4 : 0.75

Load Factor Question 3 Detailed Solution

Demand factor

\(Demand \space factor={Maximum \space demand\over Connected\space load}\)

  • For smaller motors (<10 HP), not all motors operate at full load continuously, so the demand factor is less than 1.
  • A typical range for small motor loads is 0.75 to 0.85, meaning only 75% to 85% of the connected load is expected to operate at peak demand.
  • Thus, the demand factor for motors below 10 HP should generally be around 0.75.
     

Demand factor for various loads:

  1. Residential load (over 1 kW) = 0.5
  2. Residential load (< 0.25 kW) = Less than 0.5
  3. Motor Load (< 10 HP) = 0.75
  4. Commercial load (for Restaurants) = 0.7

Load Factor Question 4:

State True/False for the following statements related to power generation:

1. Load factor is always greater than unity.

2. Diversity factor is always less than unity.

  1. False, False
  2. True, True
  3. False, True
  4. True, False

Answer (Detailed Solution Below)

Option 1 : False, False

Load Factor Question 4 Detailed Solution

Load factor

Load factor is a measure of the efficiency with which electrical energy is used.

It is defined as the ratio of the average load over a given period to the maximum load during that same period.

\(Load \space factor={Average \space load\over Maximum\space load}\)

The value of load factor is always less than 1.

Diversity factor

The sum of individual maximum demands to the maximum demand on the power station is known as a diversity factor.

\(Diversity \space factor={Sum\space of \space individual\space maximum\space demands\over Maximum\space demand\space on \space power \space station}\)

The value of load factor is always greater than 1.

Hence, statement 1 and 2 are false.

Load Factor Question 5:

The average demand of a plant is 55 MW. Find the maximum energy that can be produced if the plant is running at full load according to the operating schedule. The plant use factor is 60%.

  1. 92 MWh
  2. 792 MWh
  3. 2200 MWh
  4. 33 MWh

Answer (Detailed Solution Below)

Option 3 : 2200 MWh

Load Factor Question 5 Detailed Solution

Plant Capacity Factor (Use Factor)

This is the ratio of the actual energy produced to the maximum possible energy the plant could produce if it ran at full capacity.

\(Plant \space use \space factor={Actual \space Energy \space Produced \over Maximum \space possible \space energy}\)

Actual Energy Produced

This is calculated by multiplying the average demand by the total time (in hours). Since no time is provided, we can calculate the energy for a standard period, like one day (24 hours).

Calculation

Given, Average demand = 55 MW

Plant use factor = 60% = 0.6

Actual Energy Produced (1 day) = 55MW × 24hours = 1320MWh

Maximum Possible Energy (1 day) = \({1320\space MWh\over 0,6}=2200\space MWh\)

Top Load Factor MCQ Objective Questions

An industrial consumer has a load pattern of 2000 kW at 0.8 lagging for 12 hours and 1000 kW at unity power factor for 12 hours. Its load factor is

  1. 0.6
  2. 0.8
  3. 0.5
  4. 0.75

Answer (Detailed Solution Below)

Option 4 : 0.75

Load Factor Question 6 Detailed Solution

Download Solution PDF

Concept:

Load factor: The ratio of average load (AL) to the maximum demand (MD) during a given period is known as the load factor.

\(Load factor =\dfrac{AL}{MD}\)

If the plant is in the operation of T hours

\(Load factor = \dfrac{{AL\times T}}{{MD \times T}}\)

Note: To find Load factor, Demand Factor, Diversity Factor, etc, we used unit of Power in kW or W, and unit of Energy in kWh or Wh, not in kVA or kVAh

Application:

Given,

P1 = 2000 kW for 12 hr,

P2 = 1000 kW for 12 hr,

Since, maximum power is P1 hence,

MD = 2000 kW

Now, Average load (AL) can be calculated by the ratio of total energy consumed in kWh to the total time

\(AL=\dfrac{(2000\ kW\ \times\ 12\ hr)+(1000\ kW \times\ 12\ hr)}{24\ hr}=1500\ kW\)

From above concept,

\(Load \ factor=\dfrac{AL}{MD}=\dfrac{1500}{2000}\)

Load Factor = 0.75

The load factor of domestic load is

  1. 10 to 15% 
  2. 30 to 40% 
  3. 50 to 60%
  4. 60 to 70%

Answer (Detailed Solution Below)

Option 1 : 10 to 15% 

Load Factor Question 7 Detailed Solution

Download Solution PDF

Type of load

Demand factor

Diversity factor

Load factor

Domestic

70-100%

1.2-1.3

10-15%

Commercial

90-100%

1.1-1.2

25-30%

Industrial

70-80%

1.3-1.6

60-65%

Agricultural

90-100%

1-1.5

15-25%

The annual load duration curve is a straight line from 20 MW to 6 MW. Find the load factor.

  1. 50%
  2. 75%
  3. 85%
  4. 65%

Answer (Detailed Solution Below)

Option 4 : 65%

Load Factor Question 8 Detailed Solution

Download Solution PDF

Load Factor

Load factor is defined as the ratio of the average load over a given period to the maximum demand (peak load) occurring in that period.

\(Load \space factor={Average \space demand \over Maximum \space demand}\)

The average demand is given by:

\(Average \space demand={Area \space under \space curve \over Total \space time(in\space hrs)}\)

Calculation

F1 Vinanti Engineering 26.12.22 D1

\(Average \space demand={(6\times 8760)+(1/2\space \times \space 8760 \space \times 14 ) \over 8760}\)

Average demand = 13 MW

\(Load \space factor={13\over 20}=0.65\)

Load factor = 65%

If the maximum demand is 100 kW, the load factor is 100%, then find Units generated/annum.

  1. 876 TWh
  2. 876 Wh 
  3. 876 kWh
  4. 876 MWh

Answer (Detailed Solution Below)

Option 4 : 876 MWh

Load Factor Question 9 Detailed Solution

Download Solution PDF

Load Factor

Load factor is defined as the ratio of the average load over a given period to the maximum demand (peak load) occurring in that period.

\(Load \space factor={Average \space demand \over Maximum \space demand}\)

The average demand is given by:

\(Average \space demand={Area \space under \space curve \over Total \space time(in\space hrs)}\)

The area under the curve gives the number of units generated/per annum.

Calculation

Given, Maximum demand = 100 kW

Load Factor = 100% = 1

\(1={Average \space demand \over 100}\)

Average demand = 100 kW

For 1 year = 8760 hrs

\(100× 10^3={Area \space under \space curve \over 8760}\)

No. of units generated = 876 × 106 Wh

No. of units generated = 876 MWh

A generating station has a maximum demand of 30 MW and load factor of 60 Percent. If plant capacity factor is 45 Percent, find the reserve capacity.

  1. 12 MW
  2. 10 MW
  3. 5 MW
  4. 15 MW

Answer (Detailed Solution Below)

Option 2 : 10 MW

Load Factor Question 10 Detailed Solution

Download Solution PDF

Plant capacity factor: It is the ratio of actual energy produced to the maximum possible energy that could have been produced during a given period.

\(Plant\;capacity\;factor = \frac{{{\rm{Actual\;energy\;produced}}}}{{Maximum\;energy\;that\;could\;have\;been\;produced}}\)

Plant capacity factor \( = \frac{{Average\;demand × T}}{{Plant\;capacity × 100}}\)

Plant capacity factor \(= \frac{{Average\;demand}}{{Plant\;capacity}}\)

\(Annual\;plant\;capacity\;factor = \frac{{{\rm{Annual\;kWh\;output}}}}{{Plant\;capacity × 8760}}\)

The plant capacity factor is an indication of the reverse capacity of the plant. A power station is so designed that it has some reserve capacity for meeting the increased load demand in the future. Therefore, the installed capacity of the plant is always somewhat greater than the maximum demand on the plant.

Reserve capacity = Plant capacity – Maximum demand

If the maximum demand on the plant is equal to plant capacity, then load factor and plant capacity factor will have the same value. In such a case, the plant will have no reserve capacity.

Load factor: The ratio of average load to the maximum demand during a given period is known as the load factor.

Load factor = average load / maximum demand

Energy generated = Average load x Time (T)

Calculation:

Given that, 

Load factor = 60% = 0.6

Plant capacity factor = 45% = 0.45

Maximum demand = 30 MW

Energy generated/annum = Maximum demand × load factor × hours in a year

= 30 × 0.6 × 8760 = 157680 MWh

Plant capacity factor = (units generated/annum)/(Plant capacity × hours in a year)

Plant capacity \(= \frac{{157680{{}}}}{{0.45\; × \;8760}} = 40\;MW\)

Reserve capacity = plant capacity – maximum demand

Reserve capacity = 40 – 30 = 10 MW

Another Method:

Average demand = Load factor × Maximum demand

Average demand = 0.6 × 30 = 18 MW

Plant capacity = Average demand / Plant capacity factor

Plant Capacity = 18 / 0.45 = 40 MW

Reserve capacity = 40 – 30 

Reserve capacity = 10 MW

A 100 MW power station delivers 100 MW for 2 hours, 50 MW for 6 hours in a day and is shut down for maintenance for 45 days each year. Calculate its annual load factor?

  1. 20%
  2. 21%
  3. 22.5%
  4. 18.3%

Answer (Detailed Solution Below)

Option 4 : 18.3%

Load Factor Question 11 Detailed Solution

Download Solution PDF

Concept:

Load factor: The ratio of average load to the maximum demand during a given period is known as the load factor.

Load factor = average load/maximum demand

If the plant is in the operation of T hours

\(Load\;factor = \frac{{Avearge\;load \times T}}{{Maximum\;demand \times T}}\)

\(= \frac{{Units\;generated\;in\;T\;hours}}{{Maximum\;demand \times T}}\)

  • The load factor may be daily load factor, monthly or annually if the period considered is a day or month or year
  • Load factor is always less than 1 because the average load is smaller than the maximum demand
  • It plays a key role in determining the overall cost per unit generated
  • Higher the load factor of the power station, lesser will be the cost per unit generated, it is because higher load factor means lesser maximum demand
  • The station capacity is so selected that it must meet the maximum demand
  • Now, lower maximum demand means a lower capacity of the plant which reduces the cost of the plant

 

Calculation:

Average load \( = \frac{{100 \times 2 + 50 \times 6}}{{24}} = 20.833\;MW\)

Maximum demand = 100 MW

Number of days of plant operation = 365 – 45 = 320

Load factor \( = \frac{{20.833 \times 320}}{{100 \times 365}} \times 100 = 18.26\% \)

A power plant generates 192,000 kWh of electrical energy in a day, and its peak load is 20,000 kW, its daily load factor is:

  1. 0.004
  2. 0.40
  3. 0.04
  4. 4.0

Answer (Detailed Solution Below)

Option 2 : 0.40

Load Factor Question 12 Detailed Solution

Download Solution PDF

Concept:

Load factor: The ratio of average load to the maximum demand during a given period is known as the load factor.

Load factor = average load / maximum demand

Energy generated = Average load x Time (T)

If the plant is in operation of T hours

\(Load\;factor = \frac{{Avearge\;load \times T}}{{Maximum\;demand \times T}}\)

\(= \frac{{Units\;generated\;in\;T\;hours}}{{Maximum\;demand \times T}}\)

  • The load factor may be daily load factor, monthly or annually if the period considered is a day or month or year
  • Load factor is always less than 1 because the average load is smaller than the maximum demand
  • It plays a key role in determining the overall cost per unit generated
  • The higher the load factor of the power station, the lesser will be the cost per unit generated, it is because a higher load factor means lesser maximum demand
  • The station capacity is so selected that it must meet the maximum demand
  • Now, lower maximum demand means a lower capacity of the plant which reduces the cost of the plant

 

Calculation:

Energy generated by the power plant in a day = 192,000 kWh

Number of hours in a day = 24

Average energy generated = \( {192,000 \over 24}\) = 8,000 kW

Peak demand = 20,000 kW

Load factor = \( {8,000 \over 20,000} = 0.4\)

A consumer has a maximum demand of 300 kW at a 30% load factor. What are Units consumed/year?

  1. 78.84 Wh
  2. 7884 kWh
  3. 788400 Wh
  4. 788400 kWh

Answer (Detailed Solution Below)

Option 4 : 788400 kWh

Load Factor Question 13 Detailed Solution

Download Solution PDF

The correct answer is option 4):(788400 kWh)

Concept:

Energy consumed per annum (kWh) = ( load factor × Maximum demand  × 8760) 

8760 hours per year

Calculation:

Maximum demand = 300 kW

Load factor = 30%

Energy consumed per annum (kWh) = (300 × 0.3 × 8760) =  788400 kWh 

A system has connected load of 120 kW, peak load of 100 kW, base load of 25 kW and average load of 48 kW. The load factor of the consumer is

  1. 40%
  2. 48%
  3. 25%
  4. 83.3%

Answer (Detailed Solution Below)

Option 2 : 48%

Load Factor Question 14 Detailed Solution

Download Solution PDF

Concept:

Load factor: The ratio of average load to the maximum demand during a given period is known as the load factor.

Load factor = average load/maximum demand

Energy generated = Average load x Time (T)

If the plant is in operation of T hours

\(Load\;factor = \frac{{Avearge\;load \times T}}{{Maximum\;demand \times T}}\)

\(= \frac{{Units\;generated\;in\;T\;hours}}{{Maximum\;demand \times T}}\)

  • The load factor may be daily load factor, monthly or annually if the period considered is a day or month or year
  • Load factor is always less than 1 because the average load is smaller than the maximum demand
  • It plays a key role in determining the overall cost per unit generated
  • Higher the load factor of the power station, lesser will be the cost per unit generated, it is because higher load factor means lesser maximum demand
  • The station capacity is so selected that it must meet the maximum demand
  • Now, lower maximum demand means a lower capacity of the plant which reduces the cost of the plant

 

Calculation:

Average load = 48 kW

Peak load = 100 kW

Load factor = 48/100 0.48 = 48%

If a power station supplies 1000 MWh of electricity to its consumers for a period of two months, then the average demand during the period will be:

  1. 1.39 MW
  2. 1.39 kW
  3. 0.694 MW
  4. 0.694 kW

Answer (Detailed Solution Below)

Option 3 : 0.694 MW

Load Factor Question 15 Detailed Solution

Download Solution PDF

Concept

The average demand of a power plant is given by:

\(Average\space demand={Total\space energy\over Total \space time \space in \space hrs}\)

Calculation

Given, Total energy = 1000 MWh

Total time = 2 months = 60 days = 60 × 24 hrs

\(Average\space demand={1000\over 60\times 24}\)

Average demand = 0.694 MW

Get Free Access Now
Hot Links: teen patti classic mpl teen patti teen patti star login teen patti master old version