Download Solution PDFWith reference to tenders, which of the following statements is INCORRECT?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDF- The incorrect statement is 2) "The earnest money is never returned to the unsuccessful contractors after disposal of the tender."
- In the tendering process, earnest money is submitted by bidders to demonstrate their seriousness and commitment. However, it is a common practice to return earnest money to unsuccessful bidders once the tender process is concluded.
- The purpose of earnest money is to ensure that bidders have a genuine interest in the tender, and its return to unsuccessful bidders is a fair practice acknowledging their participation. This encourages competition and ensures transparency in the tendering process.
Last updated on Jul 1, 2025
-> SSC JE Electrical 2025 Notification is released on June 30 for the post of Junior Engineer Electrical, Civil & Mechanical.
-> There are a total 1340 No of vacancies have been announced. Categtory wise vacancy distribution will be announced later.
-> Applicants can fill out the SSC JE application form 2025 for Electrical Engineering from June 30 to July 21.
-> SSC JE EE 2025 paper 1 exam will be conducted from October 27 to 31.
-> Candidates with a degree/diploma in engineering are eligible for this post.
-> The selection process includes Paper I and Paper II online exams, followed by document verification.
-> Prepare for the exam using SSC JE EE Previous Year Papers.