Question
Download Solution PDFMinimum period before striking formwork in soffit of slabs is
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
Type of formwork | Minimum period before sticking formwork |
Vertical formwork to columns, beams, and walls | 16 - 24 hour |
Soffit formwork to slabs (props to be refixed immediately after removal of formwork) | 3 days |
Soffit formwork to beams (props to be refixed immediately after removal of formwork) | 7 days |
Props to slab | |
|
7 days |
|
14 days |
Props to beams | |
|
14 days |
|
21 days |
Last updated on May 19, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been released on its official website.
-> JKSSB JE exam will be conducted on 10th August (Civil), and on 27th July 2025 (Electrical).
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from18th May 2025 to 16th June 2025
-> Candidates who are preparing for JKSSB JE can download syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.