In the Critical Path Method (CPM), the cost-time slope of an activity is given by

This question was previously asked in
PY 1: GATE ME 2020 Official Paper: Shift 1
View all GATE ME Papers >
  1. \( {\rm{\frac{{Crash\;Cost - Normal\;Cost}}{{Crash\;Time\;}}}} \)
  2. \({\rm{\frac{{Normal\;Cost}}{{Crash\;Time - Normal\;Time\;}}}} \)
  3. \( {\rm{\frac{{Crash\;Cost}}{{Crash\;Time - Normal\;Time\;}}}}\)
  4. \( {\rm{\frac{{Crash\;Cost - Normal\;Cost}}{{Normal\;Time - Crash\;Time\;}}}}\)

Answer (Detailed Solution Below)

Option 4 : \( {\rm{\frac{{Crash\;Cost - Normal\;Cost}}{{Normal\;Time - Crash\;Time\;}}}}\)
Free
GATE ME 2023: Full Mock Test
5.6 K Users
65 Questions 100 Marks 180 Mins

Detailed Solution

Download Solution PDF

Concept:

Crash time is the minimum activity duration to which an activity can be compressed by increasing the resources and by increasing the direct cost.

The slope of the line gives the amount of increase in the direct cost per unit time for crashing an activity.

Concept:

15 7 1.1

Cost Slope: The direct cost curve is a curve that can be approximated by a straight line, depending upon the flatness of the curve. The slope of this straight is the cost slope. It is very helpful in the project cost analysis.

\({{\rm{C}}_{\rm{s}}} = \frac{{{\rm{Crash\;Cost}} - {\rm{Normal\;Cost}}}}{{{\rm{Normal\;Time}} - {\rm{Crash\;Time}}}}\)

The activity with minimum cost slope should be crashed first, as it results in optimum crashing of the project.

Latest GATE ME Updates

Last updated on Feb 19, 2024

-> GATE ME Answer Key has been released. The exam was held on 3rd, 4th, 10th, and 11th February 2024.

-> The Graduate Aptitude Test in Engineering, also known as GATE, conducts an Entrance exam that serves as a gateway for all Engineering aspirants.

->  Candidates who want a successful selection can refer to the GATE ME Preparation Tips to boost their exam preparation and increase their chances of selection.

->  Candidates must attempt the GATE ME Mock tests

More Operations Research Questions

Get Free Access Now
Hot Links: teen patti master list teen patti all app teen patti master golden india